BSOP-330 Week 5 Quiz

1.

Question :

(TCO 9, 10, & 12) The MPS

Student Answer:

must sum up to the total in the production plan.

can have any quantity necessary to meet customer demand.

is only used in make-to-stock manufacturing.

does not have to be tested for capacity limits.

2.

Question :

(TCO 12) In an assemble-to-order MPS, the items stocked in inventory are

Student Answer:

finished goods.

component parts.

raw materials.

sub-assemblies.

3.

Question :

(TCOs 9, 11, & 12) Which one of the following pieces of information would be more useful to the order entry department in a make-to-stock company?

Student Answer:

The planned order receipt file

The planned MPS released quantity file

The available to promise file

The balance of the forecast quantity

4.

Question :

(TCO 12) A forecast

Student Answer:

is always 100 percent correct.

will get better and better the more time and money you spend.

is a time prediction of the future based on the past.

is a monthly project that marketing loves to do.

5.

Question :

(TCO 10 & 12) In job shop (make-to-order) operations, the master production schedule is usually expressed in

Student Answer:

end items.

modules.

kits.

customer orders.

warehouse orders.

Photos

BSOP-330 Week 5 Quiz
$12.00 Tax included. Shipping not included.

User reviews

No reviews. Be the first to write one!

Delivery

All purchases are sent via email. Check your inbox and spam folder for an email from DevryGenius.com.

Promotions

Subscribe to our newsletter to receive special discounts and offers.

Contact us

DevryGenius.com
New York, NY 10011
support@devrygenius.com,

Newsletter

Sign up and never miss another deal.